Roadmap

February 20th, 2021

VFS-3 Testing

Load and Endurance Testing Completed

March 1st, 2021

VFS-3 Release Date

[with reservation]

February 13th, 2021

VFS-3 Testing

Load and endurance tests

February 12th, 2021

VFS-3 PCB

ETA VFS-3 PCB v1

February 12th, 2021

Website Update

Updates Completed

January 24th, 2021

VFS-3 testbench

First Prototype in test bench

February 1st, 2021

Website update

Started work on: Website layout and Shipping modules

January 18th, 2021

VFS-3 Main Components Fabrication

CNC Turning and Milling

February 14th, 2021

New ICP Batch

Start building new batch of ICP\'s

February 12th, 2021

VFS-3 Mechanical subcomponents

ETA at Vipergear Workshop

March 14th, 2021

New ICP Batch Completed

[with reservation]